Landscape membrane structure is also very common in our daily life. Its essence is a stretched membrane awning with a certain landscape effect, especially in some squares and tourist attractions. Of course, in some gardens, communities and entertainment places, the landscape membrane structure mainly plays the role of decoration, sunshade and rain protection. So what should be paid attention to when installing the landscape membrane structure? let SIGMA GROUP explain it, I hope it can be helpful to everyone.
1. The installation of landscape membrane structure includes three parts: membrane expansion, connection and fixation, and stretching. When installing the landscape membrane structure, a safety net must be installed, and the operator must fasten the seat belt. During the installation process, the staff must wear soft-soled shoes when walking on the surface of the membrane structure, and are not allowed to carry hard objects such as keys.
2. When installing the landscape membrane structure, the wind speed should not exceed the fourth level. When installing, pay special attention to the wind speed and direction to avoid shaking. At the same time, it should be decided whether to suspend and continue the project according to the amount of precipitation.
3. When the membrane structure is tensioned, the tensioning sequence and tensioning amount should be determined in batches, the tensioning speed should be controlled, and the tensioning amount should be determined according to the material properties.
4. When the next process or adjacent projects are started, protective measures must be taken to prevent damage to the structural components of the landscape membrane. In the absence of effective protective measures, welding and cutting operations within 2 meters of the membrane material are strictly prohibited.
5. During the auxiliary installation of the membrane body, the finished product must be protected and the surface of the membrane must not be damaged. There must be an insulating layer between the membrane structures, and direct contact is not allowed.
6. The assembly of the membrane structure notochord, valley cable and membrane structure anchor rod must be carried out in strict accordance with the technical standards of the membrane structure shed, and the back rope and the valley cable are tensioned in place. The construction record shall keep the tensile force value and have inspection requirements. For the tension value without inspection requirements, the tension record shall be kept.